Steoung Hav Bridge
- NR 11 Emergency Bridge
- Mean Chey Drainage Project
Project Type :
- 4 Pilling work, installation R.T 650m Bridge work
- Reconstruction of the substructure of bridge ( 361.68 cum )
Concrete Class B1 30mpa-19mm, 14.98cum Concrete C1, 30.047
Tone grade 400 Deformed protection, Gabion, 136sqm Top soil
and grassing, 240sqm, 240sqm Approach road. - 550,000 cm of Earthwork, 3 km channel excavation, realignment,
and trimming, construction of permanent access road,
construction of 3 bridges, pipe laying.